Rail Construction Costs
I wanted to have a look at prospects for rail to Chadstone and Monash Uni in this post, but Eddington has inconvenienced me somewhat. He came up with some outrageous cost estimates for rail construction – far higher than the Northern Central City Corridor Study figures I’ve been using for costing projects like a north-south tunnel and airport line.
Clearly, I can’t go on using the NCCCS figures over the Eddington ones just because I like the fact they are lower – ultimately they are both theoretical studies and it would be poor form to rank one above the other without good reason. So I’m going to take a more empirical approach, and look at the costs of two new Australian rail projects – the Mandurah rail line in Perth and the Epping-Chatswood line in Sydney. Mandurah opened a few months ago and Epping-Chatswood should open in a few months, so the cost structures facing these projects should be broadly similar to those in Melbourne. This should give a more accurate picture of what new rail projects will cost.
The NCCCS Estimates
The NCCCS, released in 2002, costs double track surface rail at$1.9m/km, overhead at $0.8m/km and signalling at $0.8m/km. That’s basically $3.5 million per kilometre of railway in 2001 dollars. Indexed to 2007 dollars, the cost is $4.12 million per kilometre for above ground double track rail, assuming no property acquisition. Stations are not included.
For deep level underground rail, the underground railway at $40 million/km and underground stations at $50 million. In 2006 dollars (the most recent full year figures the RBA has on their calculator), that’s $47.14 million for the rail and $58.93 million for the stations.
Note these figures are slightly higher than those used in my posts on a north-south tunnel and airport line. This is because they were costed in 2006 dollars (2007 dollars not available at the time), whereas the figures above are in 2007 dollars. The difference is small though.
The Eddington Estimates
Getting the actual costings in the Eddington report is actually fairly difficult. This is partly because the report is so long, but it also takes the approach of making it as difficult as possible to find detailed explanations of the costs. Getting marginal costs per km seems to be impossible, and there is a failure to even separate station and track costs. Furthermore, the costs provided are vague – the headline figure for the public transport option is between $7.5 and 8.5 billion, without really explaining why.
The best information I could get was in Appendix C of the Engineering Design and Costing Report (watch out it’s a big file). It gives us slightly lower costs – $5.9 billion for a 17km rail tunnel, $1.1 billion for a 26kmTarneit rail line and $200 million for DART; yielding a total of $7.2 billion, all in January 2008 dollars. Strangely, other parts of the report cost the tunnel at $7 billion and DART at $250-300 million – there’s no consistency.
The lowest cost figures give a per km cost of around $347 million for rail tunnel (presumably with stations included) and $42.3 million for above ground rail. The above ground rail figure is basically useless for estimating rail construction costs though, because the Tarneit line requires substantial land acquisition. Interestingly, if we assumed that the land acquisition costs were massive (and let’s remember that this line goes through farmland) and took up half of the total cost, the rail construction cost would still be 5 times what the NCCCS estimated for surface rail.
Mandurah rail cost
The recently completed Mandurah line in Perth is 70km long, and cost $960 million in 2006/07 dollars. The whole New Metro Rail project cost over $1.4 billion, but included numerous other works and the purchase of a fleet of trains. The Mandurah line has 11 stations, two of which are underground, which are included in the $960 million cost. Per km, Mandurah cost $13.7 million, including 11 stations and an underground section.
Epping-Chatswood rail cost
The soon to open Epping-Chatswood line in Sydney runs underground for 12.5 km. It cost $860 million to build. Given $860 million figure was not given a year, I’ll assume that it’s in 2002 dollars (the year the project started), giving us a cost of $984 million in 2007 dollars. The per km cost is $78.72 million. However, the Thiess portion of the project only covered tunnelling, rail and station shells. Total project cost was higher – $2.22 billion in 2007 dollars. This gives at total per km cost of $177.6 million. To find out how I calculated these figures, click here.
Conclusion
The table below sums up the $m per km construction costs as measured by the NCCCS, Eddington, Mandurah and Epping-Chatswood, measured in more or less current dollars.
|
Project/Study |
Underground rail cost |
Surface rail cost |
|
NCCCS |
41.14* |
4.12* |
|
Eddington |
347 |
42.3# |
|
Mandurah |
— |
13.7 |
|
Epping-Chatswood (Thiess) |
78.72^ |
— |
|
Epping-Chatswood (total) |
177.6 |
— |
* does not include stations
# includes land acquisition
^ includes only tunnel, rail and station shell cost
The upshot is that empirical evidence suggests that the NCCCS estimates are slightly too low (not that low – we should remember that these estimates are the only ones which allowed us to completely remove stations from the equation), and that the Eddington estimates are way way way way too high when compared with actual rail projects happening in Australia. From now on, I’ll rely more on the empirical data (alongside the NCCCS figures) when looking at potential new infrastructure.

The West (Worst) is quoting the new WA Treasurer and admirer of the scent of chairs:
==================
Only a day after announcing a $700 million blowout in 30 key infrastructure projects such as the Perth Arena, the Treasurer said the $850 million Ellenbrook railway line was now likely to cost in excess of $1.2 billion, highlighting the challenge facing the new Government to meet competing demands. Mr Buswell said the railway line would be built because it was an election pledge.
==================
Interesting that while the Liberals are trying to demonstrate the cost blowout is Labor’s fault (which I can’t see the link, but that is an aside) the line still seems to be priced at WA prices rather than NSW/Vic prices which always seem to be several orders of magnitude greater.
There is no exact map for Ellenbrook line because the planning studies have only been indicative, however, using whereis.com and planning a journey from SW Ellenbrook (Lord St) via Reid Hwy, West Swan, to Bayswater Station makes 21.6 km, which suggests $55m a km. This is largely freeway/arterial running with several overpasses and some greenfield running near the end. It is unknown whether extra tracks would be built from Bayswater into the city, or interleaved with Midland services that are already near capacity.
The opportunity to run the services via Morley Westfield might probably not happen (this, for non-WA people, would be like building a Rowville line that misses Chadstone or Monash Uni, or building a NW line that misses the big shopping and business areas of Castle Hill).
Phin
I’d like to do a very longterm project together with yourself to do a complete look at rail economics, including construction and operation.
Riccardo: the hope for Morley was always some sort of rapid transit (bus or tram) up Beaufort St, which has a long commercial strip in Inglewood. This is the route of the 66 bus route (which is limited stop), other services worth looking at are the 60 and 21/22. I don’t think it would be too hard to extend this to the railway line at Tonkin Hwy.
With a line to the airport looking likely, it seems probable that the Ellenbrook line costs included duplication of the Midland line.
Riccardo – sounds like a great idea to me – I’d love to have a really in depth look into it sometime!
cheers
Phin
It would be good if the line to Bayswater was four tracks (and six from Claisebrook?). Four tracks should be able to take all of Ellenbrook, Airport and Midland services.
A shame a NE suburbs railway couldn’t be built heading north out of Perth station so that the Armidales and Thornlies are through routed.
[...] at North Melbourne. The tunnel, at 2.5km long, would cost in the order of $867.5 million based on Eddington costs, or $196.8 million based on Epping-Chatswood costs. But we have to remember that the freight tunnel [...]
Hello webmaster
I would like to share with you a link to your site
write me here preonrelt@mail.ru